First pass yield (FPY) is the share of units that pass a process step the first time, with no retest, rework or repair. On a test line, a low FPY has two possible causes: the product really is failing, or the tester is failing good product. Finding out which comes first, because the fixes are completely different.

This article is part of our complete guide to automated test equipment (ATE). It is written for test, quality and continuous improvement engineers working on yield and retest rates.

In short

  • FPY = units passing first time ÷ units tested.
  • Multiply step FPYs to get rolled throughput yield across the line.
  • Units that fail, then pass on retest with no repair, point at the tester.
  • Fix the measurement system before chasing product causes.

How to calculate first pass yield and rolled throughput yield

FPY for one step is units that pass first time divided by units entering the step. For a line with several steps, rolled throughput yield (RTY) multiplies them, because a unit has to pass every step first time to come off the line clean.

StepFirst pass yield
Functional test98%
Calibration and trim95%
End-of-line test97%
Rolled throughput yield0.98 × 0.95 × 0.97 = 90.3%

Each step looks healthy on its own, but almost one unit in ten needs some form of retest or rework somewhere on the line.

Product or tester? Reading the retest data

Pattern in the dataMost likely causeNext step
Failed unit passes on immediate retest, no repairTester: contact, noise, settling, limits too tightGage R&R on that measurement
Failures cluster on one station or fixtureTester: station-to-station differenceCompare stations with the same units
Failures cluster by shift, operator or time of dayHandling, warm-up or environmentCheck loading method and temperature
Failures follow a component lot or supplierProductContainment and supplier quality
Failures are near one limit, never the otherOffset in the measurement or a limit set wrongCheck calibration and the limit basis
Failures repeat after repair and retestProduct or a real design margin issueFailure analysis

Log the measured value, not just pass or fail, and record whether a unit was retested and whether anything was repaired. Without that, FPY can’t tell you which row you are in.

What a false failure costs

Take a line testing 2,000 units a day with a 3% false failure rate and a 4-minute retest. That is 60 retests and 4 hours of retest time a day. At a $25/hour loaded labor rate over 250 working days, it is $25,000 a year in labor alone, before tester capacity, delays and the risk that an operator learns to retest until a unit passes.

That last risk matters most. When retest-until-pass becomes routine, real failures get through, and FPY reports stop meaning anything.

Raising FPY on a test line

  1. Measure the tester first. Run a gage R&R study on the measurements behind most failures.
  2. Match the stations. Calibrate and compensate so the same unit reads the same on every station.
  3. Fix contact and fixturing. Worn probes and loose connections are the most common cause of intermittent fails. See test fixtures.
  4. Revisit the limits. Limits should come from the product specification and the measurement uncertainty, not from habit.
  5. Control retests. Allow one automatic retest at most, log it, and flag units that pass only on retest.
  6. Then chase product causes with the cleaner data: lot, supplier, process step.

Is it the product or the tester?

Sciotex designs and improves automated test systems on any hardware and language, including NI and LabVIEW, and can assess an existing tester’s repeatability and station matching. No subscription or support contract required.

Explore our ATE systems

Frequently asked questions

What is first pass yield?

First pass yield is the percentage of units that pass a process or test step the first time, without retest, rework or repair.

How is rolled throughput yield calculated?

Multiply the first pass yields of every step in the line. Three steps at 98%, 95% and 97% give a rolled throughput yield of about 90.3%.

How can I tell if a tester is causing false failures?

If failed units pass on immediate retest with no repair, or failures cluster on one station or fixture, the tester is the likely cause. A gage R&R study confirms it.

Should retests count toward first pass yield?

No. A unit that passes only on retest did not pass first time. Count retests separately so you can see how much yield the tester is costing you.

What is a good first pass yield for a test line?

It depends on the product and the step, but the trend and the split between real and false failures matter more than one target number.

Related articles

Written by

Sciotex Engineering

The Sciotex engineering team has designed and built test, vision and automation systems since 1997.

Have a test problem to solve?

Talk it through with a Sciotex engineer.

In this article
Planning an automated test system?

Talk it through with a Sciotex engineer.

Next step

Need an automated test system that just works?